Standard or custom steel hall: what really changes in lead time and price

Standard or custom steel hall? It sounds like a choice between cheap and expensive, but it is really a choice between a frame that has already been calculated and one that still has to be. That difference moves some of the steps between enquiry and occupancy permit — but not all of them. In this article we separate what really changes in design, lead time and price from what stays the same whichever hall you choose.
What a standard hall is — and what a custom hall is
A standard steel hall has its sections, frame spacing and connection details worked out in advance, so the mass of the structure and the order of fabrication are known before a quotation exists. Modeco’s documented standard hall measures 10 × 30 × 5 m (300 m² of floor plan): 6 portal frames at 6 m centres, 12 IPE 330 columns, IPE 240 rafters with a haunch up to 500 mm, S235 steel. We dissect it element by element in the article on the 10 × 30 m hall.
A custom hall is designed the other way round: first the span, height, equipment and floor plan, then the frame that carries them. That does not mean dearer per kilogram — it means the calculation is done for that one building.
In between sits the coverage rule: a standard design is not one hall but a family of halls. In European practice for standard structural designs, a structure calculated for a span L and a frame spacing a covers any building with a smaller span and a closer spacing without a new calculation — the German standard-hall designs (bauforumstahl) allow this explicitly. The length changes by adding bays of 6 m; doors, openings and cladding are chosen independently of the frame. Once the span gets wider or the frames further apart, it is no longer the standard design but a new calculation.
What changes and what stays the same
| What | Standard hall | Custom hall |
|---|---|---|
| Structural design | The frame is already calculated; the designer checks it and adapts it to the loads of the site. | The frame is sized from scratch for the given span, height and equipment. |
| Design check (checking engineer) | Same obligation: gross floor area of 800 m² or more, or a span of 10 m or more. Our standard hall spans 10 m — it goes to the checking engineer. | Same obligation, same thresholds. |
| Route to the permit | The same statutory procedure — a standard frame does not change the level of documentation. | The same statutory procedure. |
| Execution class (EN 1090-2) | Without an overhead crane, usually EXC2. | With an overhead crane, as a rule EXC3 (fatigue verification). |
| Fabrication | A known sequence: cutting, connections, welding, protection. | Workshop drawings and preparation are produced for this one building. |
| Erection | Takes as long; anchoring, haunches and bracing are already resolved. | Takes as long; the details are worked out for the building but have never been erected. |
| Price | Published calculation: from 22,500 € excluding VAT for 10 × 30 × 5 m. | Only after the calculation, by written quotation; not necessarily dearer per kilogram. |
Lead time: where a standard frame saves time and where it does not
For a hall of around 1,000 m² in Croatia, the realistic route from enquiry to occupancy permit takes 8–15 months: paperwork 4–8 months, construction 3–6 months. The phases are the same for both kinds of hall — what differs is which of them the standard design actually shortens.
Main (or conceptual) design · 4–10 wks
The frame calculation is not done from zero — it is checked and adapted to the site.
Special conditions of public-law bodies · 30 days
A statutory deadline in Croatia; it does not depend on whether the frame is standard.
Design check — checking engineer · 2–4 wks
The obligation depends on span and area; the checking engineer's deadline is agreed by contract.
Building permit · 30–60 days
A statutory administrative deadline in Croatia, plus the appeal period until the permit becomes final.
Fabrication + foundations (in parallel) · 4–10 wks
Production preparation is shorter: the structure has been built before and the sequence is known.
Erection of structure and envelope · 3–7 wks
The crane and the erectors work the same; a standard frame saves improvisation, not the lifting itself.
Floor, services, occupancy permit · 5–12 wks
Independent of the load-bearing structure.
To be fair: most of the lead time is not drawings but procedure — special conditions, the design check and the permit take as long for a standard hall as for a custom one. A standard frame shortens the two phases that are engineering work; how many weeks that saves on your building depends on the designer and the site. Anyone promising you a standard hall “in a month”, permit included, has skipped part of the procedure. All nine phases, with statutory and market deadlines, are set out in our 2026 guide.
Price: what you pay for differently
A standard hall can have a published price precisely because its calculation has been paid for once. For our 10 × 30 × 5 m design: primary structure 7,438 kg × from 2.20 €/kg, plus Z roof purlins, secondary members and fixings — from 22,500 € excluding VAT in total. Divided by 300 m² of floor plan that is about 75 €/m², but for the steel structure only: no envelope, foundations or erection. The item-by-item calculation is in the article on the price of a prefabricated hall in 2026.
A custom hall is priced only once its calculation is finished, by written quotation. Three things move that figure more than the label “custom”:
- 01Span, height and crane determine the sections, and the sections determine the mass. A wider span or an overhead crane means heavier columns and rafters — a difference in kilograms, not in the price per kilogram.
- 02Steel grade changes the mass on the same geometry: S355 instead of S235 takes around 17 % off the frame mass (bauforumstahl, standard-hall designs), but S355 costs more per kilogram. Two quotations with different grades can describe the same hall.
- 03Connections are under 5 % of the frame mass but over 30 % of the cost of fabrication (SCI P358). A structure optimised for minimum mass can lose on the connections what it saved on steel.
And the most important point for the budget: the structure is typically only 20–33 % of a turnkey investment. Choosing between a standard and a custom hall moves that share; it does not change the foundations, envelope, services or public charges.
Permit and design check in Croatia: the same route
A standard solution shortens the design work, but it does not change the statutory procedure. Three Croatian rules apply equally to both kinds of hall:
- ·A design check by a checking engineer is mandatory for a gross floor area of 800 m² or more, or a span of 10 m or more (Ordinance on Design Checking NN 32/14, 72/20, 90/23, Art. 3). Our standard hall spans exactly 10 m, so it is checked even though it has only 300 m².
- ·An agricultural building of up to 600 m² of gross floor area gets its permit on the basis of the conceptual design (Building Act NN 155/25, Art. 62) — step by step. Commercial, warehouse and production halls go on the main design (Art. 64).
- ·The detailed design with workshop drawings is produced before works start (Art. 39) — for a standard hall too; it is not mandatory only for less complex buildings, such as an agricultural hall of up to 600 m².
The standard design is calculated for continental Croatia. Snow, wind and ground conditions at your site are checked by an authorised designer; where loads are higher, the sections grow — then either a heavier standard design is confirmed or the frame is calculated to measure. The execution class to EN 1090-2 does not depend on the label either: if the design does not state one, EXC2 applies, and a hall with an overhead crane as a rule moves to EXC3. Modeco’s production is certified for EXC3, so it covers both cases.
Checklist: standard or custom
If you can answer “yes” to all five points, a standard solution probably suits you:
A span of up to 10 m without a central column is enough for you.
The floor plan is rectangular — no extensions, cantilevers or skewed walls.
There is no overhead crane and no heavy suspended equipment in the hall.
An eaves height of about 5 m is enough for you.
You can adjust the length in frame steps and choose openings and cladding freely.
One “no” does not mean a dearer hall — it means the frame is sized for your case instead of being taken ready-made. The first four questions are also available as a short tool on the standard steel halls page, and if you are still choosing use and size, see which hall you need.
Standard or custom · an answer with figures
Send us the dimensions, use and location — we will tell you whether the standard design fits and how heavy the structure will be.
For the standard hall the calculation is published; for a custom hall we quote after the calculation, with the same item structure. Only a written quotation is binding.
* Sections, mass and price apply to the standard structure 10 × 30 × 5 m and a continental climate; figures are starting prices (“from”), excluding VAT. Lead times are market ranges for a hall of around 1,000 m² in Croatia, except the statutory deadlines for special conditions and the permit. The final sizing follows from the structural calculation for the specific site.
Frequently asked questions
A standard steel hall is built to a repeatable frame calculated in advance: the sections, frame spacing and connection details are known before the quotation, so the mass of the structure and the order of fabrication are known too. Modeco's standard hall measures 10 × 30 × 5 m, with IPE 330 columns and IPE 240 rafters with a haunch. A custom hall has its frame sized from scratch for the specific building.
English version of the Croatian original: Tipska ili hala po mjeri: što se stvarno mijenja u roku i cijeni.